The Arrangement of the slab foundation of the 12th floor at "Alizi Mukhiani" has finished, and work on the top floor columns and roofing slab has begun.The following are completed in Alizi Mukhiani project:
The installation of PVC doors and windows on the 7th floor, as well as the completion of the block wall arrangement on the 9th floor, is scheduled for February. The plastering of the facade has also begun.
As a result, 92 % of the frame monolithic construction works have been finished.