At Alizi Mukhiani the arrangement of the slab foundation of the ninth floor (on the +32.30 points) is finished. The installation of vertical columns and diaphragms of the roof slab is in progress.
The arrangement of the block walls including the fifth floor is completed. The process of installing PVC doors and windows and the electrical wiring of the apartments continues. The plastering work of interior walls is in progress as well.
In November, the installation of windows, floor to ceiling windows, and electricity supply of the apartments are planned.
77% of the frame-monolithic construction works of the Alizi Mukhiani project has already been completed.